Skip to main content

Capital Project

Capital Project

Germantown CSD Capital Project Banner

 

Approved!

 

On Tuesday, December 19, 2023, voters in the Germantown Central School District approved a $13.9 million capital project referendum that prioritizes safety, accessibility, and opportunity for students and staff. For more information on the proposed project, see below.

 

Project Communications

 

Voting Communications / Information

 

Smart Schools Bond Act (2023) 

Previous Completed Capital Project Archive

2023 Capital Project Update

Phase One Status 

We have reviewed all projects with Architect and Construction team to submit all required documents to NYSED for approval. Everything for Phase one was received by SED on March 4, 2024. SED has three review processes for phase one of our project, Architectural Review, Engineering Review, then Financial Review. 

Architectural Review – Completed 

Engineering Review – Completed.

Financial Review – Completed. 

The District is now putting all projects in Phase One out to bid. We anticipate to be able to start projects in the Spring of 2025. 

We plan to build the playground with the community and will be looking for volunteers to help. More information with be provided as we get closer to Spring. 

 

Phase One Projects: 

Playground on Main Street 

Roof Repair 

RTU Replacement  

 

 

Phase Two Status 

We have reviewed all projects with Architect and Construction team to submit all required documents to NYSED for approval. Everything for Phase two was received by SED on July 12, 2024. SED has three review processes for phase one of our project, Architectural Review, Engineering Review, then Financial Review. 

SED PROJECT REVIEW STATUS AS OF 08/28/2024:

  • Architectural Review:
    • Average time for final architectural review will be about 14-16 weeks.
    • The next architectural review will be 23-1971. It was logged into the review system on 05/13/24.
  • Engineering Review:
    • Average time for final engineering review will be about 26-28  weeks.
    • The next engineering review will be 23-1506.  It was logged into the review system on 02/16/24.

Phase Two Projects: 

Locker Room Renovation 

Bathroom Renovation 

Door Replacement 

Lockdown Functions 

Phase Three Status 

We are currently working on all designs for phase three with our Architect and Construction team. Phase three should be ready for submission by the end of October 2024. We will provide updates and design drawings as we progress forward. 

Updated Interior Finishes GCSD BOE Presentation (11/14/24)

Phase Three Projects 

Demo Old Maintenance Garage Design
New Maintenance Facility Addition SED Review
Address Basement Flooding Bid
Outdoor Speakers Construction
Repave Main Street Parking Lot
Sewer Line to 9G
Emergency Road to Sports Fields
Steps to Cafeteria Entrance
Sidewalk around Auditorium
Chairlift to Ramp Conversions
Update Power Boxes in Tank Room
Replace Outside Lighting on Main St
Replace Select Flooring
Paint Hallway Walls
Generator